Internal inspection: 2026-06-30. Publisher completion: October 2026. Payment label: Pay 1% Monthly. Status: Sold out.
Danube Properties · Developer-published · Checked 19 Jul 2026Construction source ↗ · Project source ↗
Studio–3 bedroom apartments · 801 residences by Danube Properties in Jumeirah Village Circle (JVC).
Checked 25 Oct 2026
These are changes in developer-published information, not changes to your contract or government confirmation. Publisher pages can change; earlier figures are our dated observations, not archived copies of the current page.
Internal inspection: 2026-06-30. Publisher completion: October 2026. Payment label: Pay 1% Monthly. Status: Sold out.
Danube Properties · Developer-published · Checked 19 Jul 2026Internal inspection: 2026-09-30. Publisher completion: December 2027. Payment label: 30/70 Payment Plan. Status: Sold out.
Danube Properties · Developer-published · Checked 25 Oct 2026Compare your actual contract completion date and dated payment schedule with the current dated developer update. The 30/70 label alone does not provide every obligation, date, fee or remaining balance; a complete schedule is not attached to this research.
Review the contract checklist · Compare a complete payment schedule
No. The label alone does not give the due dates or triggers. Our 25 Oct 2026 observation of Danube’s Elitz 2 page recorded “30/70 Payment Plan”; our 19 Jul 2026 observation recorded “Pay 1% Monthly”. Neither label supplies a complete schedule, and the newer label does not establish which terms apply to your purchase.
Ask for each amount, due date or payment trigger. The label does not establish payment at handover, after handover or in one instalment.
Ask whether the 1% wording applies to the offer you are considering, what amount that percentage uses and how many payments it covers. Do not combine the two labels into a new plan.
Ask for the agreed price, any separate charges and the balance after payments already made. A payment split is not an all-in cost or a statement of your remaining balance.
Please send the dated Elitz 2 payment schedule for the offer I am considering, identifying the project phase and unit. For each instalment, please show the amount or percentage basis and due date or trigger, including the timing of the 70%. Please confirm whether the 1% monthly wording applies, list separate charges and reconcile any payments already made.
Danube project source ↗ · Checked 25 Oct 2026; earlier label checked 19 Jul 2026. Historical explanation added 30 Oct 2026, not a new check of the publisher pages; the separate 31 Oct reading above is a later source check. Earlier labels are retained observations, not archived copies.
Compare a complete payment schedule once you have the actual terms. This page does not calculate obligations from either marketing label.
The important answers first. Information not yet available is turned into a clear question to confirm.
Sold out on Danube's website.
Danube Properties update dated 30 Sept 2026.
The developer's stated date may change.
Current selling price not confirmed from the sources checked.
The developer says “30/70 Payment Plan”, but we could not verify every payment and date.
Recent project sales not confirmed from the sources checked.
Shown on the project information checked.
Use these with the developer, agent or adviser. They make it easy to ask for the newest source and keep the conversation clear.
Could you please share the current official selling price, including the unit, currency and date?
Could you please share the complete dated payment schedule, including fees and the remaining balance?
Could you please share the newest official construction update and inspection date for this exact project and phase?
See how Danube's published progress changed over time. The archive shows what Danube published at that time; it is not a government inspection.
Percentage points means the later figure minus the earlier figure. This compares figures we recorded on two visits; it is not a new construction verification or a forecast. Check dates are when we read the page. Inspection dates are the dates the developer supplied. The source links may now show newer information.
The figure rose from 28% to 34% (28% → 34%).
Earlier observation · 28% · Checked 19 Jul 2026
Inspection date: 30 Jun 2026
Danube Properties · Inspection source checked 19 Jul 2026 · Earlier inspection source ↗
Danube Properties · Source checked 19 Jul 2026 · Earlier construction source ↗
Later observation · 34% · Checked 25 Oct 2026
Inspection date: 30 Sept 2026
Danube Properties · Inspection source checked 25 Oct 2026 · Later inspection source ↗
Danube Properties · Source checked 25 Oct 2026 · Later construction source ↗
Mobilization completed; shoring in progress; piling design approved; building permit received; main contractor on board.
Archived copy · Checked 20 Jul 2026View archived proof ↗Danube reported 6.30% after an internal inspection dated 31 Aug 2024.
Archived 12 Sept 2024 · Checked 20 Jul 2026View archived proof ↗Danube reported 14% after an internal inspection dated 31 Jan 2025.
Archived 8 Feb 2025 · Checked 20 Jul 2026View archived proof ↗Danube reported 28% after an internal inspection dated 30 Jun 2026.
Current developer page · Checked 19 Jul 2026View current update ↗Danube reported 34% after an internal inspection dated 30 Sep 2026; checked 25 Oct 2026.
Current developer page · Checked 25 Oct 2026View current update ↗These links open Danube Properties pages in a new tab.
We matched the exact project name and phase across the developer's project and construction pages. We checked the pages on 25 Oct 2026.
The 34% construction figure is from Danube Properties and uses an inspection date of 30 Sept 2026. It is not a government inspection.
A brochure link is not shown because the file could not be opened and matched reliably.
Short answers based on the pages checked.
Danube Properties' website showed “Sold out” when we checked on 25 Oct 2026. Resale or assignment units may still be available elsewhere.
Danube Properties' construction page showed 34%, with an inspection date of 30 Sept 2026. This is the developer's update, not a government inspection.
We could not verify a current selling price from the pages checked. We do not reuse old listing prices.
The developer uses the phrase “30/70 Payment Plan”, but we could not verify every payment, date and remaining balance.
Danube Properties stated December 2027 when we checked on 25 Oct 2026. The date may change.